57.3-KM SECTOR OF 160-KM “NORTH-SOUTH” ARTSAKH ROAD ALREADY BUILT,
CONSTRUCTION OF 40.2 KM UNDERWAY

YEREVAN, MARCH 17, NOYAN TAPAN. The construction of 57.3-km sector of
the “North-South” Artsakh road lasted 5 years, the 40.2-km sector is
still being built. According to the Executive Committee of “Hayastan”
(“Armenia”) pan-Armenian fund, the construction in the “Vanki
Khachmeruk – Kichan,” “Kichan – Drmbon,” “Stepanakert – Chanakhi
Khachmeruk,” “Azokh – Tsakuri,” “Tsakuri – Hadrut” road sectors is
underway. And the construction of the “Drmbon – Martakert” and
“Chanakhi Khachmeruk – Sarushen” sectors will begin in April-May. A
tender has been announced for the construction of the above-mentioned
2 sectors.