Energetic outputs of the republic will get considerable acquisition
hp
Norayr Hovsepyan.
17-02-2010
`Artsakhhes’ OJSC has already 1111 shareholders. The capital of the
company has increased from 100 millions to 6 milliard drams. The
collected sum has been directed to the construction of new
hydroelectric power stations.
Shareholders of `Artsakhhes’ have already a chance to estimate the
first results of the works. But they are more than obvious.
Program of construction of small hydroelectric power stations started
from Trghe-1, constructed on the nearest hill of Haterk village.
Construction of the building began in April of 2009 and ended in the
end of December. Today corresponding equipments have been already put,
technical director of `Artsakhhes’ Armen Gasparyan informes. The whole
value of the program compiles 820 million drams, works of about 760
million have been done.
It’s only one side of the question, Except additional reserves of
electricity, Trghe-1 will satisfy additional working places. A new
subdivision has been already formed with 31 working places in the
stuff of `Artsakhhes’. Today the newly formed subdivision has still 13
workers. Pressure pool of Trghe-2 is already ready. It’s near Trghe-1.
They have already ordered equipments. During this month construction
of the building will start. Trghe-2 will be put into operation in
March-April 2011. But works in Trghe-1 will end in two months.
The next building of Trghe cascade will be Trghe-3.
In administrative territory of Mataghis community construction works
are not stopping. Works in hydroelectric power stations Mataghis-1 and
Mataghis-2 will end in defined period of time, executives of the
sphere assure. `Technoshin’ CJSC realizes works in Mataghis-1 and
Mataghis-2. Water examiner, leading knot of Mataghis-1 is already
ready, assembly works of pipes are going to end. Construction of base
of hydroelectric power station has already begun, director of
`Technoshin’ CJSC Garik Petrosyan represents.
In general, works of 1 milliard 450 million drams have been realized
in Mataghis-1. And the whole value of the program compiles 2 milliard
600 million drams. In mataghis-2 works are in the process. Here
construction works of pressure pool of water examiner and leading knot
ended. Assembling of pipes has begun.
Executives of construction make believe, that the works will be
finished in defined period of time. It means, that hydroelectric power
stations Mataghis-1 and Mataghis-2 will be put into operation in a
year – in January-March 2011.